Project Completed on different site by SWAT Lab

S.No.

Name of the Project (Consulting service)

Location

Value of Contract (in NRs.)

Year Completed

Name of the Client

Description of worked carried

1.

  • Baseline Monitoring (Survey and Analysis) of Water Analysis, Ambient Air Quality, and Noise Level Monitoring of Chainpur Seti Hydropower Project, Nepal Electricity Authority

Sankhuwasabha, Chainpur Municipality

NRs. 2,00,000

Dec-2020

Nepal Electricity Authority

The main task of the consulting services was:

  • Identification of sampling sites

  • Set up of Air and Noise Instruments at the specific sites and monitor air quality and Noise Level

  • Onsite Physical properties Testing of water of the projects at each identified point

  • Collect water samples from the identified point to analysis different parameters

  • Analysis the sample collected in Lab with national standard

  • Prepare environmental baseline report with major content

    • methodology of data collection

    • data analysis methodology

    • major findings

interpretation of data with national standards for each project

2.

Survey and Sampling of Water Quality Monitoring of 26 water supply schemes of Sindhupalchok District for OXFAM Nepal

Sindhupalchok

NRs. 70,000

Dec-2018

OXFAM, Nepal

  • Identification of sampling sites

  • Water Quality Monitoring ofwater supply schemes

  • Onsite Physical properties Testing

  • Collect water samples from the identified point to analysis different parameters

S.No.

Name of the Project (Consulting service)

Location

Value of Contract (in NRs.)

Year Completed

Name of the Client

Description of worked carried

      
  • Analysis the sample collected in Lab with national standard

3.

Survey Collection and characterization of fecal sludge samples for SNV Nepal, the Netherlands

Nepalganj

NRs. 230,859

Dec-2020

SNV Nepal

  • Identification of sampling sites

  • Collect fecal Sludge from the identified point to analysis different parameters

  • Analysis the sample collected in Lab

  • methodology of data collection

  • data analysis methodology

  • major findings

S.No.

Name of the Project (Consulting service)

Location

Value of Contract (in NRs.)

Year Completed

Name of the Client

Description of worked carried

4.

Baseline Monitoring (Survey and Analysis) of Air Quality, Noise Quality and Physio-Chemical Properties of Soil and Water of

  1. EIA of Betan Karnali Peaking Run of River of Hydroelectric Project(439 Mwp)

  2. EIA of Phukot Karnali Peaking Run of River of Hydroelectric Project(480 Mwp)

  3. EIA of Jagdulla Peaking Run of River of Hydroelectric Project(106 Mwp)

  4. EIA of Kimathanka Arun Hydroelectric Project(450 Mwp)

  5. IEE Study of Haitar- Sitalpati (Arun Corridor) 400 Kv Transmission Line Project

  6. IEE Study of Mewa- Change 132 Kv Transmission Line Project

Dolpa, Mugu, Humla, Sankhuwasabha District

NRs. 1514290.04

Dec-2022

NEA Engineering Company Ltd.

The main task of the consulting services was:

  • Identification of sampling sites

  • Set up of Air and Noise Instruments at the specific sites and monitor air quality and Noise Level

  • Onsite Physical properties Testing of water and soil of the projects at each identified point

  • Collect water and Soil samples from the identified point to analysis different parameters

  • Analysis the sample collected in Lab with national standard

  • Prepare environmental baseline report with major content

    • methodology of data collection

    • data analysis methodology

    • major findings

    • interpretation of data with national standards for each project

S.No.

Name of the Project (Consulting service)

Location

Value of Contract (in NRs.)

Year Completed

Name of the Client

Description of worked carried

5.

Baseline Monitoring (Survey and Analysis) of Air Quality, Noise Quality and Physio-Chemical Properties of Soil and Water of

  1. Affected Areas of Dudh Koshi Hydroelectric Project

Khotang, Solukhumbu, Solukhumbu

NRs.427,976.2

Aug-22

NEA, Environment and Social Studies

Department

(ESSD)

Main Task

  1. Identification of sampling sites

  2. Set up of Air and Noise Instruments at the specific sites and monitor air quality and Noise Level

  3. Onsite Physical properties Testing of water and soil of the projects at each identified point

v. Collect water and Soil samples from the identified point to analysis different parameters

v. Analysis the sample collected in Lab with national standard

vi. Prepare environmental baseline report with major content

ii. methodology of data collection

ii. data analysis methodology

x. major findings

x. interpretation of data with national standards for each project

S.No.

Name of the Project (Consulting service)

Location

Value of Contract (in NRs.)

Year Completed

Name of the Client

Description of worked carried

6.

Sampling and Analysis of Air, Stack, Noise, and Wastewater Quality Test for A.A.C. Itta Udhyog Gajuri-5, Dhading

Dhading, Nepal

NRs. 2,55,468.5

Feb-2022

A.A.C. Itta Udhyog

The main task of the consulting services was:

  • Identification of sampling sites

  • Set up of Stack, Air and Noise Instruments at the specific sites

  • Analysis the sample collected in Lab with national standard

  • Prepare Report with including

    • methodology of data collection

    • data analysis methodology

    • major findings interpretation data with national standards

S.No.

Name of the Project (Consulting service)

Location

Value of Contract (in NRs.)

Year Completed

Name of the Client

Description of worked carried

7.

Survey and sampling and Conduct the test on water, Solid Waste, waste water, and Fecal sludge for IWSSMP Project.

Pokhara, Butwal, Lumbini, Mahendranagar, Nepalganj, Dhangadi

NRs.303859.8

Oct, 2022

BDA-SWS JV in

association Sub Consultany with SAP, Kamladi, Kathmandu

  1. Identification of sampling sites

  2. Onsite Physical properties Testing of water at each identified point

  3. Collect water, Waste water, fecal Sludge and Solid waste from the identified point to analysis different parameters

  4. Analysis the sample collected in Lab

  5. methodology of data collection

  6. data analysis methodology

  7. major findings

8.

  • Wastewater Analysis, Flow Measurement (Gokarna and

Hanumanghat), Fecal Sludge (Selected

Location of Kathmandu and Near Areas)

Gokarneshwor Hanumanghat

NRs. 1,81,560.4

July-2022

TEAMS-BCPC-JV

  1. Identification of sampling sites

  2. Onsite Physical properties Testing of waste water at each identified point

  3. Collect Waste water and fecal Sludge from the identified point to analysis different parameters

  4. Analysis the sample collected in Lab

  5. methodology of data collection

  6. data analysis methodology

  1. major findings

S.No.

Name of the Project (Consulting service)

Location

Value of Contract (in NRs.)

Year Completed

Name of the Client

Description of worked carried

9.

Water Quality (Physio- Chemical Properties of River Water) of different Hydroelectric Projects

  1. Physio-chemical properties of River Water of Super Budhigandaki Hydroelectric Project (SBGHEP)

  2. Physio-chemical properties of River Water of Tom Doger (Budhigandaki) Hydroelectric Project (TBGHEP)

  3. Physio-chemical properties of River Water of Upper Budhigandaki Hydroelectric Project (UBGHEP)

  4. Physio-chemical properties of River Water of Kaligandaki Storage Hydropower Project (KGSHPP)

  5. Physio-chemical properties of

River Water of Surnayagad Hydropower Project (SGHPP)

Mugu, Karnali, Gorkha, Darchula District

NRs.1550550.60

Dec-22

Innovative Engineering Services Pvt Ltd

  • Identification of sampling sites

  • Onsite Physical properties Testing of water of the projects at each identified point

  • Collect water samples from the identified point to analysis different parameters

  • Receiving and Coding Water Sample

  • Analysis the sample collected in Lab with following Standard Methodology

  • Prepare Lab analysis report with major content

  • data analysis methodology

  • major findings

  • interpretation of data with national standards for each sample with related projects

S.No.

Name of the Project (Consulting service)

Location

Value of Contract (in NRs.)

Year Completed

Name of the Client

Description of worked carried

 
  1. Physio-chemical properties of River Water of Naugad Hydropower Project (NGHPP)

  2. Physio-chemical properties of River Water of Simbuwa Khola Hydroelectric Project (SKHEP)

  3. Physio-chemical properties of River Water of Super Budhigandaki Hydroelectric Project (SBGHEP)

  4. Physio-chemical properties of River Water of Hima Khola Hydroelectric Project (HKHEP)

  5. Physio-chemical properties of River Water of Lugri Khola Hydropower Project (LKHPP)

  6. Physio-chemical properties of

River Water of Lower Badigad Hydropower Project (LBHPP)

     

S.No.

Name of the Project (Consulting service)

Location

Value of Contract (in NRs.)

Year Completed

Name of the Client

Description of worked carried

 

xii) Physio-chemical properties of River Water of Mugu Karnali Hydroelectric Project (MKHEP)

     

10.

Air Quality Testing, Water Quality Analysis and Noise Level Analysis for Mugu Karnali Storage Hydroelectric Project, 1902MW (MKHEP)

Bajura District

8,64,043.2

Feb-2,2023

Jade Consult Pvt. Ltd. Thapathali, Kathmandu

Main Task

  1. Identification of sampling sites

  2. Set up of Air and Noise Instruments at the specific sites and monitor air quality and Noise Level

ii. Onsite Physical properties Testing of water of the projects at each identified point

v. Collect water samples from the identified point to analysis different parameters

v. Analysis the sample collected in Lab with national standard

vi. Prepare environmental baseline report with major content

ii. methodology of data collection

ii. data analysis methodology

x. major findings

x. interpretation of data with

S.No.

Name of the Project (Consulting service)

Location

Value of Contract (in NRs.)

Year Completed

Name of the Client

Description of worked carried

11.

Air Quality Testing, Water Quality Analysis and Noise Level Analysis for Simbuwa Khola Hydroelectric Project, 70.3MW (MKHEP)

Taplejung District

4,66,600

April-1,2023

Jade Consult Pvt. Ltd. Thapathali, Kathmandu

Main Task

  1. Identification of sampling sites

  2. Set up of Air and Noise Instruments at the specific sites and monitor air quality and Noise Level

  3. Onsite Physical properties Testing of water of the projects at each identified point

v. Collect water samples from the identified point to analysis different parameters

v. Analysis the sample collected in Lab with national standard

vi. Prepare environmental baseline report with major content

ii. methodology of data collection

ii. data analysis methodology

x. major findings

x. interpretation of data with national standards for each project

S.No.

Name of the Project (Consulting service)

Location

Value of Contract (in NRs.)

Year Completed

Name of the Client

Description of worked carried

12.

Air, Noise Monitoring, Stack Emission, Water Analysis of International Green Developers Nepal Pvt. Ltd., Jagati, Bhaktapur

Bhaktapur District

1,46,900

April-28,2023

International Green Developers Nepal Pvt. Ltd.

Main Task

  1. Identification of Sampling Sites.

  2. Set up of Air ,Stack and Noise Instruments at the specific Sites and Monitor Air quality, Stack and Noise Level

  3. On Site Physical Parameters Testing of water

  4. Collect water Samples From the identified point to analysis different parameters

  5. Analysis the sample Collected in Lab with National Standard

  6. Prepare environment baseline report with major content

  7. Methodology of data collection

  8. Data Analysis Methodology

  9. Interpretation of data with national standard

S.No.

Name of the Project (Consulting service)

Location

Value of Contract (in NRs.)

Year Completed

Name of the Client

Description of worked carried

13.

Air Quality, Noise Monitoring, Water Analysis of Dandhakhet- Rahughat Transmission Line Project.

Myagdi District , Beni

47,819.34

May-8,2023

L&T Construction

Main Task

  1. Identification of Sampling Sites.

  2. Set up of Air and Noise Instruments at the specific Sites and Monitor Air quality and Noise Level

  3. On Site Physical Parameters Testing of water

  4. Collect water Samples From the identified point to analysis different parameters

  5. Analysis the sample Collected in Lab with National Standard

  6. Prepare environment baseline report with major content

  7. Methodology of data collection

  8. Data Analysis Methodology

  9. Interpretation of data with national standard

S.No.

Name of the Project (Consulting service)

Location

Value of Contract (in NRs.)

Year Completed

Name of the Client

Description of worked carried

14.

Air Quality, Noise Monitoring, Water Analysis of Arun Khola Dumkibas 132/33/11 KV Transmission Line Project.

Nawalpur District

65,687

May-12,2023

Godrej and Boyce mfg.co.Ltd.

Main Task

  1. Identification of Sampling Sites.

  2. Set up of Air and Noise Instruments at the specific Sites and Monitor Air quality and Noise Level

  3. On Site Physical Parameters Testing of water

  4. Collect water Samples From the identified point to analysis different parameters

  5. Analysis the sample Collected in Lab with National Standard

  6. Prepare environment baseline report with major content

  7. Methodology of data collection

  8. Data Analysis Methodology

  9. Interpretation of data with national standard

S.No.

Name of the Project (Consulting service)

Location

Value of Contract (in NRs.)

Year Completed

Name of the Client

Description of worked carried

15.

Air Quality, Noise Monitoring, Water Analysis of Jadibuti, Tinkune and Koteshwor.

Bhaktapur and Kathmandu District.

89,462.1

May-15, 2023

Full Bright

Consultancy Pvt. Ltd.

Main Task

  1. Identification of Sampling Sites.

  2. Set up of Air and Noise Instruments at the specific Sites and Monitor Air quality and Noise Level

  3. On Site Physical Parameters Testing of water

  4. Collect water Samples From the identified point to analysis different parameters

  5. Analysis the sample Collected in Lab with National Standard

  6. Prepare environment baseline report with major content

  7. Methodology of data collection

  8. Data Analysis Methodology

  9. Interpretation of data with national standard

S.No.

Name of the Project (Consulting service)

Location

Value of Contract (in NRs.)

Year Completed

Name of the Client

Description of worked carried

16.

Water Quality Analysis of three different District of Nepal. (Bara, Parsa and Rautahat)

Bara, Parsa and Rautahat District.

6,59,920

May, 2023

ERMC- ARAGON – GOLDEN -JV

Main Task

  1. Identification of Sampling Sites.

  2. On Site Physical Parameters Testing of water

  3. Collect water Samples From the identified point to analysis different parameters

  4. Analysis the sample Collected in Lab with National Standard

  5. Interpretation of data with national standard

17.

Air Quality Monitoring of Asphalt Plant in Pokhara, Kaski

Kaski District

1,13,000

July-13,2023

Green Road Waste Management Pvt. Ltd.

Main Task

  1. Identification of Sampling Sites.

  2. Set up of Air Sampling Instruments at the specific Sites and Monitor Air quality.

  3. Analysis the sample Collected in Lab with National Standard

Interpretation of data with national standard

S.No.

Name of the Project (Consulting service)

Location

Value of Contract (in NRs.)

Year Completed

Name of the Client

Description of worked carried

18.

Air Quality Monitoring, Water Quality Analysis and Noise Level Analysis of Purnagiri Water Supply and Sanitation Sector Project.

Kanchanpur District

1,21,475

July-23,2023

Kankai Ganapati JV

Main Task

  1. Identification of Sampling Sites.

  2. Set up of Air and Noise Instruments at the specific Sites and Monitor Air quality and Noise Level

  3. On Site Physical Parameters Testing of water

  4. Collect water Samples From the identified point to analysis different parameters

  5. Analysis the sample Collected in Lab with National Standard

  1. Interpretation of data with national standard